Guam Transportation Program: Multiple traffic advisories this week
The Guam Transportation Program is advising community members of various construction zones beginning Monday, Feb 3. 2025 and expected until Sunday, Feb. 9, 2025.
Motorists are advised to drive cautiously through the construction zones, observe all posted speed limit and construction signs, and carefully heed flaggers (when present).
Alternate routes and/or adjusting drive times when feasible are encouraged.
Route 14B (Ypao Road) Reconstruction and Widening (Route 14 to Carmen Memorial Dr), Phase 1 Cliffside – Tamuning
- From Monday, Feb. 3 to Friday, Feb. 7, between 9 a.m. and 4 p.m., motorists are advised that the contractor will continue shoulder work along Route 14B and on the sidewalk. During this time, expect minimal lane shifts and intermittent lane closures.
Route 14 Resurfacing from Route 1 to Route 14B – Tamuning
- On Monday, Feb. 3, motorists are advised that the contractor will resume shoulder work along Route 14 (Chalan San Antonio) southbound near the Baltej Pavilion. Work will occur between 9 a.m. and 4 p.m. throughout the week. During this time, expect minimal lane shifts and intermittent lane closures.
Islandwide Village Street Pavement Resurfacing – Agat Village
- The DPW HMC crew will be milling and paving North Santa Cruz St and San Antonio de Padua St in Agat Village. Work will occur between 7 a.m. and 4 p.m. The DPW asks motorists and residents to proceed with caution and remain alert for traffic control signs and work crews.
Route 1 Striping – Route 29 to AAFB
- The DPW HMC crew will be stripping Route 1 Marine Corps Dr from the Our Lady of Lourdes Catholic Church to Andersen Air Force Base. Work will occur between 8 a.m. and 3 p.m. The DPW asks motorists and residents to proceed with caution and remain alert for traffic control signs and work crews.
Route 1 Grass Cutting – Upper Tumon
- The DPW HMC crew will be grass cutting Route 1 Marine Corps Dr starting in upper Tumon working north. Work will occur between 8 a.m. and 3 p.m. The DPW asks motorists and residents to proceed with caution and remain alert for traffic control signs and work crews.
Route 15 Grass Cutting – Mangilao/Yigo
- The DPW HMC crew will be cutting grass Route 15 starting in Mangilao working north towards the AAFB Back Gate. Work will occur between 8 a.m. and 3 p.m. The DPW asks motorists and residents to proceed with caution and remain alert for traffic control signs and work crews.
GTP also advises of fines that could be incurred:
- Failure to Yield at Intersection - $100
- Fail to Yield to Pedestrian (intersection) - $200
- Failure to Yield Right-of-Way - $80